Which of the following is NOT one of the benefits in MRP?
A) improved utilization of facilities and labor
B) better response to customer orders as the result of improved adherence to schedules
C) increased inventory levels
D) faster response to market changes
C) increased inventory levels
Which of the following statements is NOT true about MRP?
A) MRP uses a bill-of-material, inventory, expected receipts, and a master production schedule to determine material requirements
B) MRP is an independent demand technique used in a production environment
C) MRP has evolved as the basis for Enterprise Resource Planning
D) MRP provides a clean structure for dependent demand
B) MRP is an independent demand-based technique used in a production environment
What is an information system for identifying and planning the enterprise-wide resources needed to take, make, ship, and account for customer orders?
A) MRP
B) SCM
C) EIS
D) ERP
D) ERP
Which of the following statements is NOT true?
A) for any product for which a schedule can be
established, different techniques could be used
B) less inventory frees up capital and floor space for other uses
C) demand for items is dependent when the relationship between the items can be determined
D) for any product, some components of that product are independent demand items
D) for any product, some components of that product are independent demand items
What is a list of quantities of components, ingredients, and materials required to make a product?
A) master production schedule
B) engineering change notice
C) bill-of-material
D) purchase order
C) bill-of-material
Which of the following pieces of information is NOT contained in a bill-of-material?
A) physical dimensions
B) raw material to be used
C) lead times
D) quantities of components
C) lead times
Which of the following allows a segment of the master schedule to be designated as "not to be rescheduled?"
A) pegging
B) time fence
C) freeze point
D) system nervousness
B) time fence
The operations manager has two important tools available to deal with MRP system nervousness. Those tools are:
A) time fences and
pegging
B) pseudo bills and kits
C) buckets with black flush
D) net and gross requirements
A) time fences and pegging
Which of the following tools means tracing upward in the BOM from the component to the parent item?
A) pegging
B) time fencing
C) system nervousness
D) bucketing
A) pegging
Which of the following is NOT true about MRP limitations?
A) MRP does not tell you that a job needs to be completed on a certain week or day
B) MRP is an excellent tool for product-focused and repetitive facilities, but it has limitations in process (make-to-order) environments
C) MRP does not do detailed scheduling
D) MRP is considered an infinite scheduling technique
A) MRP does not tell you that a job needs to be completed on a certain week or day
What is the lot-sizing technique that generates exactly what was required to meet the plan?
A) Wagner-Whitin
B) periodic order quantity
C) lot-for-lot
D) economic order quantity (EOQ)
C) lot-for-lot
Which of the following lot-sizing techniques is likely to prove the most complex to use?
A) economic order quantity (EOQ)
B) periodic order
quantity (POQ)
C) lot-for-lot
D) Wagner-Whitin
D) Wagner-Whitin
What is a lot-sizing technique that orders the quantity needed during a predetermined time between orders?
A) POQ
B) part time balancing
C) EOQ
D) Wagner-Whitin
A) POQ
Which of the following statements is NOT true about the EOQ?
A) The EOQ
can be a reasonable lot-sizing technique when demand is relatively constant and independent
B) The EOQ is a statistical technique using averages, whereas the MRP procedure assumes known demand reflected in a master production schedule
C) The EOQ can be used as a lot-sizing technique for MRP systems
D) The EOQ is preferable when dependent demand exists
D) The EOQ is preferable when dependent demand exists
What provides feedback to the capacity plan, master production schedule, and production plan so planning can be kept valid at all times?
A) closed-loop MRP system
B) system nervousness
C) MRP II
D) lot sizing
A) closed-loop MRP system
What sends a lot to two different machines for the same operation?
A) operations splitting
B) lot splitting
C) pegging
D) overlapping
A) operations splitting
What is a report showing the resource requirements in a work center for all work currently assigned there, as well as all planned and expected orders?
A) load report
B) closed-loop report
C) MRP II report
D) pegging report
A) load report
What is the act of breaking up an order and running part of it ahead of schedule?
A) operations splitting
B) overlapping
C) pegging
D) lot splitting
D) lot splitting
What is a time-phased stock-replenishment plan for all levels of the supply chain?
A) BOM
B) MRP
C) DRP
D) MRP II
C) DRP
Which of the following statements is NOT true about DRP?
A) the goal of a DRP
system is small and frequent replenishment within the bounds of economical ordering and shipping
B) Effective use of DRP requires an integrated information system to rapidly convey planned order releases from one level to the next.
C) The DRP procedure starts with the forecast at the supplier level
D) When dependent techniques are used in the supply chain, they are called distribution resource planning (DRP)
C) The DRP procedure starts with the forecast at the supplier level
A bill of materials for a menu item in a restaurant is also called a:
A) product specification
B) recipe
C) food bill
D) bill of ingredients
A) product specification
Which of the following statements about DRP is NOT true?
A) DRP procedures and logic are analogous to MRP
B) DRP stands for "distribution resource
planning"
C) lead times are considered in DRP
D) DRP pushes inventory through the system
D) DRP pushes inventory through the system
*it actually pulls
What is an information system for identifying and planning the enterprise-wide resources needed to take, make, ship, and account for customer orders?
A) BOM
B) MRP
C) ERP
D) CIM
C) ERP
Which of the following is an advantage of ERP?
A) it is simple enough that companies have an easy time adjusting to it
B) data fields do not have to be defined identically across the entire enterprise
C) it is very inexpensive to purchase
D) it creates commonality of databases
D) it creates commonality of databases
Which of the following statements is NOT true regarding ERP?
A) ERP allows companies share a common database and business practices throughout the enterprise
B) ERP usually provides financial and human resource management information
C) the objective of an ERP system is to coordinate a firm's whole business
D) ERP promises slow, but accurate, information
D) ERP promises slow, but accurate, information
Supply chain management systems in the grocery industry that tie sales to buying, to inventory, to logistics, and to production are called
A) grocery resource planning
B) efficient consumer response
C) distribution resources planning
D) enterprise resource planning
B) efficient consumer response
Sets with similar termsISDS 3115 CH 14 study plan concepts
26 terms
mburle7525
Ch. 14 MRP and ERP
28 terms
laurenarseneau
OPS chapter 14
42 terms
Kristen_Hisek
ISDS 3115 Ch. 14
14 terms
morgan_kastner
Sets found in the same folderCH 14
28 terms
molly_longo
ISDS 3115 CH 16 study plan concepts
16 terms
mburle7525
Chapter 7 Homework/Quiz
18 terms
Vishal_Patel1
MANGT 421: Chapter 16
18 terms
mdhammett28
Other sets by this creatorGeography 1001 Exam 1 Study Guide
95 terms
quizlette3054911
ISDS 3115 Chapter 16 Concept Questions
16 terms
quizlette3054911
ISDS 3115 Chapter 13 Concept Questions
24 terms
quizlette3054911
ISDS 3115 Chapter 12 Concept Questions
16 terms
quizlette3054911
Other Quizlet sets
chapters 6 & 8 practice exam
44 terms
keerthana_sivakumar
LSU ISDS 3115: Ch. 12 Test Bank
93 terms
monawarchabayta
AIS Chapter 7
40 terms
nicolemesina_
SCM 186 Final (Chapter 14- Materials Requirement P…
26 terms
jonathan_spinnell
Related questionsQUESTION
What kind of volcano is Mt St Helen and Mt Shasta?
8 answers
QUESTION
How can you BEST assist law enforcement at the scene of a crime involving a gunshot wound or stabbing?
15 answers
QUESTION
What type of seismic waves arrive at a seismograph first?
15 answers
QUESTION
What is George Orwell's birth name?
15 answers